Multiple digesters at a large midwestern plant, roughly 500 miles from the Somerset yard. At that distance there is no local depot to fall back on — everything that rolls in has to keep running for the duration.
The site photograph shows the spread on arrival: an MSS mixing tank with integrated access platform and railing, suction lines run out, and one of our own tractors alongside. Full drawdown, on-site dewatering, confined-space cleaning and disposal followed, with our own generators supplying site power rather than tying into plant service.
173 days on site, September 2023 through to the following spring — one crew, one schedule, and the same equipment on the pad from the first day to the last.
This job ran under Digester cleaning. Working a vessel like this one? Send us dimensions and rough volume and we will tell you what the job takes.